We take honor in assisting Petroleum industry
for the development of explored fields by
providing dependable technological options
for oil and gas production and processing.
Salient features of some of the projects
carried out recently are given below:
|
 |
 |
El-Wastani Phase III Development Project |
 |
 |
|
Location: Egypt
Client:
WASCO
Capacity:
Phase I= 5000 BPD Cond. & 157 MMSCFD of Gas, Phase II= 5200 BPD Cond. 2600 BPD LPG, 153 MMSCFD
Year of Completion:
2006
|
|

|
| |
|
| Scope: Basic and detailed Engineering, Procurement, Fabrication, Construction Supervision, Commissioning.
|
| |
 |
 |
Tangri Upgradation Project |
 |
 |
|
Location: Sindh, Pakistan
Client:
BP Exploration & production Inc.
Capacity:
15 MMSCFD
Year of Completion:
2002
|
|

|
| |
|
| Scope: Supply of Amine Sweetening Unit
|
| |
 |
 |
Amine Sweetening Unit for Block 22 |
 |
 |
|
Location: Sindh, Pakistan
Client:
Pakistan Petroleum Limited
Capacity:
20 MMSCFD
Year of Completion:
2000
|
|

|
| |
|
| Scope: Supply of amine based gas sweetening facility on semi turnkey basis
|
| |
|
Location: Sindh, Pakistan
Client:
BHP Petroleum Pty. Ltd.
Capacity:
70 MMSCFD
Year of Completion:
2000
|
|

|
| |
|
| Scope: Supply of gas processing facility comprising of inlet separation, JT valve based hydrocarbon dewpoint control and glycol based gas dehydration.
In addition, the mechanical and E&I construction work at site for whole facility was also carried out.
|
| |
 |
 |
Mazarani Gas Field Development |
 |
 |
|
Location: Sindh, Pakistan
Client:
Pakistan Petroleum Limited
Capacity:
12 MMSCFD
Year of Completion:
2003
|
|

|
| |
|
| Scope: EPCC of a complete gas processing facility comprising of inlet separator, amine based gas sweetening, glycol based gas dehydration, gas compression and plant utilities.
|
| |
|
Location: NWFP, Pakistan
Client:
MOL Pakistan Oil & Gas Company B.V.
Capacity:
50 MMSCFD
Year of Completion:
2005
|
|

|
| |
|
| Scope: EPCC of a complete gas processing facility comprising of raw gas flow line, Inlet separation, turbo expander, glycol based gas dehydration and plant utilities.
|
| |
 |
 |
Rehmat Gas Field Development |
 |
 |
|
Location: Sindh, Pakistan
Client:
Petronas Carigali (Pakistan) Limited
Capacity:
80 MMSCFD
Year of Completion:
2005
|
|

|
| |
|
| Scope: EPCC of a complete gas processing facility comprising of raw gas flow lines, inlet separation, amine based gas sweeting, silica gel based water and hydrocarbon dew point control, acid gas incineration, hot oil heater and plant utilities.
|
| |
Package
Supply
In addition to numerous EPCC jobs, we have supplied
skid mounted production & processing equipment including
three phase separators, dehydration and amine sweetening
units of wide ranging capacities to various clients.
|
|
| |
|
|
|