Oil Stabilization Package

(on going)

Location: Gambat South GPF-IV (Shahdadpur) Sindh
Client: Pakistan Petroleum Limited
Capacity: 1500BPD
Scope: Design & Supply of Oil Stabilization Package with PLC Control

White Oil Pipeline MOGAS Project (WOPMP)

(on going)

Location: Sindh, Punjab-Pakistan
Client: Pak-Arab Pipeline Co. Ltd. (PAPCO)
Capacity: Enhancement of WOP, 8.0 MTPA to 12.0MTPA
Scope: EPCC of Complete Facility

Crude Distillation Unit Revamp Project

2017

Location: Karachi-Pakistan
Client: National Refinery Limited
Capacity: Enhanced from 50000 BPD to 53000 BPD
Scope: EPCC of CDU Revamp

Gambat South Gas Processing Facility (GPF-||) Project

2017

Location: Distt. Sanghar, Sindh-Pakistan
Client: Pakistan Petroleum Limited
Capacity: 50 MMSCFD Gas Processing LPG 11 MTPD, Condensate 1050 BPD
Scope: EPCC of Complete Facility

Adhi LPG & NGL Recovery Plant |||

-

Location: Dist. Rawalpindi, Pakistan
Client: Pakistan Petroleum Limited
Capacity: 30 MMSCFD LPG 164 MPTD, NGL 5330 BPD
Scope: EPCC Complete Facility

Makori Field Development Surface Facilities

2014

Location: Karak, KPK, Pakistan
Client: MOL Oil & Gas Company B.V
Capacity: Gas Processing 150 MMSCFD, LPG 427 MTPD, Oil 20000 BPD, Condensate 10000 BPD
Scope: EPCC of the Complete Processing Facility.

Adhi EPF Upgradation Project

2013

Location: District Rawalpindi, Pakistan
Client: Pakistan Petroleum Limited
Capacity: 25 MMSCFD Gas processing capacity
Scope: Adhi EPF Up-Gradation project & modification of existing separators

Sulfur Recovery Unit- Dakhani Expansion Project

2013

Location: Punjab, Pakistan
Client: Oil & Gas Development Company Ltd.
Capacity: 90 Metric Ton per day
Scope: Design, supply & Commissioning

Standby Dehydration Unit

2009

Location: Sindh, Pakistan
Client: Pakistan Petroleum Limited
Capacity: 130 MMSCFD
Scope: EPCC of Complete unit and integration with existing plant

Manzalai Field Development Surface Facilities

2009

Location: NWFP, Pakistan
Client: MOL Oil & Gas Company B.V.
Capacity: 300 MMSCFD
Scope: EPCC of the Complete Processing Facility

El-Wastani Gas Field Development Project Ph-III

2006

Location: Damietta, Egypt
Client: El-Wastani Petroleum Co.
Capacity: 157 MMSCFD Ph-I & 153 MMSCFD Ph-II
Scope: Overall project management, construction supervision and commissioning of entire facility. All utilities on EPC basis

Gurguri Gas Field Development Project

2005

Location: NWFP, Pakistan
Client: MOL Oil & Gas Company B.V.
Capacity: 50 MMSCFD
Scope: EPCC of the Complete Processing Facility

Rehmat Gas Field Development Project

2005

Location: Sindh, Pakistan
Client: Petronas Carigali (Pakistan) Limited
Capacity: 80 MMSCFD
Scope: EPCC of the Complete Processing Facility

Mazarani Gas Field Development Project

2003

Location: Sindh, Pakistan
Client: Pakistan Petroleum Limited
Capacity: 12 MMSCFD
Scope: EPCC of the Complete Processing Facility
trunkey-projects-53200e5f22b0a.jpg